At the moment, the buildings are being cleaned and the performance of all systems is being checked; the recommendations given as a result of the safety review are being implemented: constant monitoring has been arranged – lights have been installed, visual inspection is being carried out, surveying will be regularly performed. In those areas that still remain closed further research is being done into the necessity of strengthening the structures further. A full list of which buildings are available can be found here (in Russian).

Copies of the expert recommendations after the safety review of the building are available at the links below (in Russian):

- building 1-M;

- building 3- В and E;

- building 4.

Parts of the buildings open from March 19, 2019 (in Russian)

First Floor
First Floor

Second Floor
Second Floor

Third Floor
Third Floor

Fourth Floor
Fourth Floor

Fifth Floor
Fifth Floor

You can also view the map of these areas in PDF in Russian.